C&TS shop report

friscobob May 6, 2003

  1. friscobob

    friscobob Staff Member

    10,534
    714
    129
    Form Mike Harbour on the Railspot Yahoo!Group:

    CTSRR Shop Report 5/3/03

    Posted By: Jay
    Date: Saturday, 3 May 2003, at 3:04 p.m.


    Report given by Mark Yates to The Commission, on 5/3/03.

    Any typos are mine, from scanning the report.

    Notes on Shop Work for Commission Meeting, 3 May 2003 Locomotive Work
    The following is a breakdown of locomotive work since the March 15th
    Commission meeting:

    484
    Work continues on the tender. The replacement of rivets is nearly
    complete.
    The wood between the tender frame and tank has been replaced and the
    tank is
    back on the frame.

    The sandblasting of the water space around the firebox is complete,
    The steel sub floor and cab supports have been replaced with new steel.

    487
    New shoes and wedges were picked up April 18th and are in the process
    of
    being milled to the proper dimensions.

    New hub liners have been installed on all of the drivers and are being
    faced
    to provide the proper lateral along with the driving boxes being
    babbitted
    and faced.

    Once these two steps are complete, driver sets can begin going up and
    tramming beginning with the No. 3 Drivers. It is hoped that sometime
    next
    week the No. 3 Drivers will be installed.

    The pistons and piston rods have been sent off to have the grooves
    built up
    and machined for new piston rings. This should be completed by the
    middle of
    next week.

    The pilot truck is being repaired and should be ready to replace this
    coming
    week.

    At present, all of the Chama Shop Crew's efforts are being concentrated
    on
    completing 487 in time for this operating season.

    488
    Little has been done to 488. The water space around the firebox will be
    sandblasted in the next couple of weeks.

    Passenger Cars
    The new car wheels have arrived. They still must be sent to have the
    worn
    wheels pressed off and new wheels pressed onto the old axles. I hope to
    get
    the purchase order completed and approved and to get the wheels to the
    machine shop this coming week.
    A second wheelchair lift has been purchased and received to be
    installed in
    the handicap car typically used on the Chama side to provide greater
    safety
    and service to our passengers. This will eliminate the need to cross
    the
    main line to board or disembark passengers confined to wheelchairs. A
    solar
    panel to charge the battery and a larger battery will also be instated.

    Other
    The slotter arrived March 24th and was moved into the machine shop. It
    has
    been wired and some tooting has been purchased. The machine, while
    functional, is missing some parts. For optimum performance, it requires
    about $10,000.00 worth of parts which have been ordered. The parts will
    take
    about 7-8 weeks to arrive as they have to be manufactured.

    A fair amount of time was spent leveling the east shop track inside the
    enginehouse to better facilitate leveling and tramming locomotives.
    The Kershaw Ballast Regulator is in the process of being modified. I
    visited
    with Soni Honegger on Tuesday, 29th April and it appears they are
    making
    good progress.

    The Antonito Shop Crew has been working on repairing and improving the
    steel
    flat car used to haul equipment to worksites. It is being outfitted
    with
    ramps and come-alongs to raise the ramps as well as repairing and
    beefing up
    the frame on ramp end. It will be used to haul needed equipment for the
    contractor to effect repairs at Windy Point.

    The Antonito Shop Crew has also been working on Diesel Locomotive 19 to
    put
    ft in better repair.

    The "Railroad injury and illness Summary" report for the month of March
    has
    been sent to the Federal Railroad Administration. The report for the
    month
    of April is being compiled. I am pleased to report that since the end
    of
    November there have been no reportable injuries.

    Respectfully submitted,
    Mark V. Yates
     
  2. friscobob

    friscobob Staff Member

    10,534
    714
    129
    Here's how they can afford some of the work. From the TRAINS Newswire:

    Cumbres & Toltec Scenic receives million-dollar grant

    SANTA FE, N.M. – The U.S. Commerce Department is giving a $1 million grant to the Cumbres & Toltec Scenic Railroad Commission.

    The money will help rebuild the C&TS’s historic steam locomotives. The narrow-gauge railroad, which operates on the former Denver & Rio Grande Western line, carries tourists between New Mexico and Colorado from spring into fall each year. New Mexico and Colorado jointly own the 64-mile line that runs between Chama, N.M., and Antonito, Colo.

    Railroad officials said earlier this month the train will make limited runs this season – one-way trips Sundays through Wednesdays – because only one of its locomotives will be ready. A bus will pick up passengers and return them to the train's departing depot.

    The Federal Railroad Administration has told the railroad that the boilers for the steam-powered locomotives must be improved to meet federal standards before the season starts. The federal money comes from a fund that promotes the use of historic properties and resources for economic development and heritage tourism. The railroad commission and the state of New Mexico matched the grant with $250,000.
     
  3. BoxcabE50

    BoxcabE50 HOn30 & N Scales Staff Member TrainBoard Supporter

    67,694
    23,246
    653
    Sure hope they can get another steamer up and running soon!

    Just wondering- What is the work at Windy Point? Possibly similar to what was done in another location last year?

    :D

    Boxcab E50
     

Share This Page