    The North Coast Rail Authority has issued the call for the following repair
    work on the Northwestern Pacific Railroad:

    1. Repairs to the revetments alongside the NWP tracks in Eureka between MP
    279.37 to MP 280.0 (3,100 feet). Additionally, from MP 279.37 and MP 279.5
    (500 feet), the track will be relocated 8 feet east of the existing trackway.
    This section of track is currently hanging in the air and will need to be
    filled with sand and gravel. Bids were due on 9/7/2007, and work most be
    completed within 26 weeks of bid award.

    2. Repairs to 43 Timber Bridge structures between Lombard and Windsor. Bids
    are due on 9/24, and work must be completed within 23 weeks after the contract
    is awarded.

    3. Rehabilitate the existing track between Lombard and Windsor (36 miles).
    This work will include track construction, tie replacement and surfacing,
    ballast restration, switch repair, bank and ditch improvement, grade crossing
    repairs and other miscellaneous work as required to bring this line up to
    freight train standards. Bids are due on 10/1/2007, and work must be completed
    in 30 weeks after this contract is awarded.
     